Hourly Picovale meter flow with the total order, the AKT and Bear River orders, Bear River's reported actual (from pump reports), and the implied AKT use (meter − Bear River actual; overflow not subtracted, so an upper bound) — all left axis in cfs — plotted against the North Ditch gate setting (right axis, inches), Aug 14 – Aug 20. Bear River actual and implied-AKT lines break where no pump report exists:
| Date | Time | Gate (in) | Change | Set by |
|---|---|---|---|---|
| 2026-08-17 | 05:00 | 12.4 | Raised from 8.4″ current | Henry |
| 2026-08-14 | 11:25 | 8.4 | Lowered from 8.75″ | Henry |
| 2026-08-13 | 05:10 | 8.75 | Lowered from 10″ | Henry |
| 2026-08-12 | 09:40 | 10 | Raised from 9.5″ | Ben |
| 2026-08-07 | 09:50 | 9.5 | Lowered from 10″ | Henry |
| Source | CFS | Effective start | Effective end | Notes |
|---|---|---|---|---|
| Bear River | 5 | 2026-08-05 07:00 | ongoing | Stands until changed |
| AKT | 20 | 2026-08-17 07:00 | ongoing | Stands until changed |
Current standing orders total 25 cfs. Orders are due 24 h ahead of a 7am delivery.
At an unchanged 12.4″ gate, flow is holding near 24.4 cfs (24-h average), running essentially on order (about 0.6 cfs under). Selected hourly readings (full series in master.csv):
| Date | Time | cfs | Diverted (AF) | Note |
|---|---|---|---|---|
| 2026-08-20 | 02:00 | 24.80 | 2.050 | |
| 2026-08-20 | 03:00 | 24.50 | 2.025 | |
| 2026-08-20 | 04:00 | 25.50 | 2.107 | |
| 2026-08-20 | 05:00 | 24.10 | 1.992 | |
| 2026-08-20 | 06:00 | 24.10 | 1.992 | |
| 2026-08-20 | 07:00 | 25.20 | 2.083 | Latest latest |
Prior full day (8/19) diverted 51.8 AF over 24 hours.
The gate is at 12.4″ (set 8/17). Recent daily-average flow: 16.2 (8/16), 24.9 (8/17), 28.8 (8/18), 26.1 (8/19), 24.3 (8/20). The 24-h mean is 24.4 cfs with scatter min 22.7, max 29.6, SD 1.7 — supply is running essentially on order (about 0.6 cfs under).